Cancún clears its old General Hospital site for a mother and child hospital with more than 100 beds

On September 23, Quintana Roo's governor, Mara Lezama, and the mayor of Benito Juárez, Ana Paty Peralta, launched the demolition of Cancún's old General Hospital to clear the site for a new IMSS-Bienestar mother and child hospital with more than 100 beds. One hospital is coming down so that one built around pregnancy, birth and early childhood can go up in its place, in a city that registers between 27 and 40 births a day.
For anyone who arrived in Cancún after 2017, the old hospital has simply been a large empty building in Supermanzana 65, a residential district near the center of the city. According to the state government, it opened 36 years ago and served for 27 of them. Por Esto reports that it was the city's main general hospital until March 2017, when its services moved to the current Hospital General Dr. Jesús Kumate Rodríguez in the Arco Norte area, and the old building has stood unused since.
The demolition
The municipality is doing the demolition, on a schedule the state gives as September 21 to November 14, 2026. Speaking at the site, Lezama asked people passing the area to take care while machinery is working. Luces del Siglo reports that the streets around Supermanzana 65 will see partial closures over those weeks as heavy machinery and dump trucks come and go. The mayor told El Momento Quintana Roo that the building has about 9,000 square meters of construction, that the work would run through October and that she expected it to finish in early November. The state's health secretary, Flavio Carlos Rosado, and the council's secretary general, Pablo Gutiérrez Fernández, joined the governor and the mayor at the launch.
The site sits near the junction of Avenida José López Portillo and Avenida Francisco I. Madero, according to earlier reporting by Caribe Peninsular, and the building belongs to the state government. Lezama described the change in plain terms: a space with no use since 2017 is being given a new social purpose, centered on what she called one of the most important stages of life, birth.

What the new hospital is meant to hold
The plans announced by the state describe a hospital for pregnant women, newborns and children. It is to have more than 100 beds, seven consulting rooms and three operating rooms, with specialist services in neonatology, pediatrics, gynecology, obstetrics and perinatology, an emergency department and neonatal intensive care units. It is also to have a laboratory, pathology and a diagnostic area with an X-ray room with fluoroscopy, two portable X-ray units and two ultrasound machines. "It will be infrastructure designed to care for pregnant women, newborns, children and the families of Cancún," Lezama said.
The state government puts the projected investment at almost 640 million pesos, covering construction and equipment together. It presents the hospital as a joint project of the state and federal governments, with the backing of President Claudia Sheinbaum, and says IMSS-Bienestar, the federal health service for people without social security, has added the Cancún hospital to its program for strengthening hospital infrastructure in Quintana Roo. Por Esto places it within a wider list that also includes new hospitals in Chetumal, Felipe Carrillo Puerto and José María Morelos and a specialties tower at the Jesús Kumate hospital in Cancún.

The case for it is made in numbers the city already keeps. According to the Benito Juárez civil registry, cited by the state, Cancún records an average of between 27 and 40 births a day. The governor said the new hospital would give women more security during pregnancy, bring specialist care closer to mothers, and give newborns care with the right staff, technology and space.
What is settled and what is not
The demolition is the part with dates attached. The hospital itself has not reached that stage. The state says the project begins this year, and the mayor said the aim is for construction to move ahead once the site is cleared, but no construction start date, no contractor and no opening date were given at the launch. The 640 million pesos is the state's projection for building and equipping the hospital, not a contract value. Even the demolition carries two slightly different end points: November 14 in the state's announcement, early November in the mayor's own estimate.

What has changed is that the site is no longer waiting. A building that stood empty for close to a decade in the middle of a residential district is being taken down on a published timetable, and the land has a stated use in public health.
For families who live in Cancún, the practical question over the coming weeks is the traffic around Supermanzana 65 while the demolition runs. The larger one, when the city gets a dedicated mother and child hospital, has no answer yet, and we will report the construction dates when the state or IMSS-Bienestar publishes them. For more on the city, see our Cancún page, which carries the homes we list there, in Puerto Cancún, and our earlier reports on the Kukulcán interchange and the removal of abandoned boats from the Nichupté lagoon.
Sources: Government of Quintana Roo, Coordinación General de Comunicación, announcement of the start of demolition of the old General Hospital, Cancún, September 23, 2026, as carried by Noticaribe and Milenio the same day; Heraldo de México Quintana Roo, Alexis Nolasco, September 23, 2026; Por Esto, September 24, 2026, for the March 2017 transfer to the Jesús Kumate hospital and the wider hospital program; El Momento Quintana Roo, Ángel Pérez, September 23, 2026, for the mayor's remarks on the building's size and timetable; Luces del Siglo, Ignacio Calva, September 23, 2026, for Supermanzana 65 and the street closures; Caribe Peninsular, January 30, 2025, for the site's cross streets. Main image: "City Hall, Cancun, Quintana Roo, Mexico," by Sharon Hahn Darlin, CC BY 2.0, via Wikimedia Commons.

Itza II | 2 Bedroom Furnished Apartment with Private Jacuzzi in Aldea Zama, Tulum

Maison Siscolino | 4 Bedroom Villa with Swim Up Pool and Rooftop Plunge Pool in Region 15, Tulum
Maison Siscolino, Region 15 Tulum. Furnished four bedroom villa, 245 m² on a 301 m² lot with swim up pool and rooftop plunge pool.
Follow our Tulum market reporting in Google.
Add to preferred sourcesWe are the ultimate guide to invest in Tulum
The complete guide to buying property in Tulum. Find homes for sale, condos or land and consult with an experienced real estate advisor.

News: Real Estate, Lifestyle and Growth Across the Riviera Maya
The latest from Tulum, the Riviera Maya and the Mexican Caribbean, from market trends and investment opportunities to lifestyle and the infrastructure shaping the coast.